A practical guide, built on EU GMP Annex 16 and the batch certification discipline we apply at Sciom, to the documentation, testing and quality-system gaps that hold batches in quarantine, and how to close them before the Qualified Person opens the file.
Why batches wait: the real cause of release delays
Until a Qualified Person (QP) certifies it, a finished batch cannot be sold or supplied. EU GMP Annex 16 is clear that batches should only be released for sale or supply to the market after QP certification, and that until then a batch stays at the site of manufacture or is shipped under quarantine to an approved site. Every day a batch sits in quarantine is a day of stock that cannot reach the market, and often a day of difficult conversations with the marketing authorisation holder (MAH).
Here is the useful part: most delays are caused by preventable issues, such as testing bottlenecks, documentation gaps and late quality involvement, rather than by the QP decision itself. They are built in early: a regulatory document that was never requested, a deviation that was never closed, a temperature record that nobody chased, a certificate of analysis that bounced between reviewers. By the time the QP opens the file, the gap is already there.
This article walks through where release stalls, what Annex 16 expects the QP to be assured of, and the practical controls that keep a batch moving, from the first request to the MAH and contract manufacturing organisation (CMO) through to transfer to saleable stock.
At a glance
- Annex 16 makes the QP responsible for assuring that each batch was manufactured and checked in line with the law, the marketing authorisation (MA) and GMP, however many sites are involved.
- Most delays come from missing or inconsistent evidence, not from the QP decision.
- Start the document request, sampling and QA checks as early as possible, and run them side by side.
- Close deviations and OOS investigations before the file reaches the QP.
- Treat labelling, storage and release mechanics as part of certification, not an afterthought.
What Annex 16 expects from QP certification
Annex 16 (EudraLex Volume 4: Certification by a Qualified Person and Batch Release ) is the reference point for QP certification. Several of its principles explain exactly why gaps in the file translate into delay:
- The QP carries the batch. The QP must ensure that all necessary steps were completed under accepted pharmaceutical quality systems, regardless of how many sites were involved in manufacture, importation, testing and storage.
- Imports have extra steps. For products manufactured outside the EU, physical importation and certification are the final stages of manufacturing before transfer to saleable stock. The QP must take the storage and transport conditions of the batch and sample into account.
- Reliance has to be justified. The QP may delegate tasks to trained personnel or third parties, but needs ongoing assurance that reliance on the pharmaceutical quality system is well founded.
- A long list of assurances sits behind one signature. From supply chain documentation and audit reports to technical agreements, validated state, stability and the closure of investigations.
A note on scope: Annex 16 is an EU guideline. Sciom’s batch certification procedure applies its principles for QP certification in the UK, alongside the Human Medicines Regulations 2012, which define the QP in UK law (regulation 41). Where UK and EU requirements differ, the QP and the MAH should confirm which applies to the batch in question.
Seven places batch release stalls, and how to stop it
1. An incomplete or out-of-date regulatory package
The QP certifies against the MA, so the QP needs the current MA. Annex 16 requires that all sites of manufacture, analysis and certification comply with the terms of the MA for the intended territory, that activities match those described in the MA, and that post-marketing commitments have been addressed.
- Ask the MAH at the outset for the updated marketing authorisation, including any post-approval comments.
- Obtain and review mock-ups and approved artwork for packaging materials.
- Track post-approval commitments and ongoing variations with the MAH, so that nothing changes mid-review.
2. Gaps in the manufacturing documentation from the CMO
Batch records are the backbone of the file. The documents the CMO supplies should be checked against the approved regulatory package, not just collected. Agree the full list with the CMO before the batch ships, and review:
- The Batch Manufacturing Record and Batch Packaging Record, with batch size, API calculation and potency aligned to the approved package.
- API, excipient and primary packaging release COAs, with current specifications and testing procedures matching the marketing registration.
- Analytical and microbiology method validation, process validation and stability data.
- Nitrosamine and elemental impurity risk assessments, excipient risk assessments and the TSE/BSE compliance declaration.
- The finished product COA and certificate of conformity, including any batch non-conformance records such as deviations and OOS results.
3. A supply chain, audit and agreement trail that cannot be shown
Annex 16 expects the entire supply chain of the active substance and medicinal product, up to the point of certification, to be documented and available to the QP, preferably as a comprehensive diagram that includes subcontractors of critical steps. Audit reports must be available and required technical agreements must be in place. When the QP relies on third-party audits, Annex 16 expects a written final assessment and approval of those audit reports.
- Keep a current supply chain diagram for every product, and refresh it when a site or supplier changes.
- Verify the name, address and manufacturing licence of the finished product and packaging sites against the regulatory package and the relevant GMP database.
- Confirm that a quality technical agreement exists between the manufacturing site and the MA holder or MIA holder, and between Sciom and the storage site and any contract testing laboratory.
4. Transport and storage evidence that nobody has reviewed
Temperature excursions and unreviewed goods receipt records are classic last-minute surprises. Because the QP must consider storage and transport conditions before certification, this evidence needs to be ready early:
- Verify the storage site’s name, address, WDA licence number and validity.
- Review goods receipt documents, including temperature data or transport route validation.
- Have the storage site confirm that the batch looks physically satisfactory and has not suffered adverse conditions in transit.
- Hold the batch in quarantine and sample only once the consignment is confirmed appropriate.
5. Testing that starts late or is not planned
Sampling, sample transfer and testing sit on the critical path. Annex 16 expects imported product to be sampled representatively of the whole batch and responsibilities for sampling to be defined in writing. In practice:
- Send samples and a test request form to the testing site as soon as the documentation review allows, with the specification and standard testing procedure to be followed.
- Confirm that the analytical method transfer requirements are met before samples arrive, so testing is not paused for method questions.
- Verify the GMP licence and technical agreement of any contract testing laboratory up front.
- Collect retention and reference samples at the same time, and store them in compliance with the product’s storage conditions (our process holds retention samples for one year after expiry).
6. A certificate of analysis that needs rework
The COA is the document the QP leans on most. If it is wrong, release stops. Prepare it in a controlled system, have QA review and approve it, and only then pass it on to the QP. At Sciom, COAs are generated in our Pharma Plus system, and a QA review checks that results comply with the specification before the COA goes to the QP. A confirmed result outside specification triggers an investigation, not a workaround.
7. Open deviations, OOS results and unlabelled risks
This is the most common reason a batch that looks ready is not. Annex 16 asks the QP to be assured that all investigations pertaining to the batch, including out-of-specification and out-of-trend investigations, are complete to a sufficient level to support certification, and that ongoing complaints, investigations or recalls do not negate the conditions for certification.
Annex 16 also recognises that not every deviation is fatal. Provided registered specifications are met, a QP may consider certifying a batch after an unexpected deviation, if it has been thoroughly investigated and the root cause corrected. The impact should be assessed through quality risk management, including evaluation of the potential impact on quality, safety or efficacy and a conclusion that the impact is negligible.
- Record deviations, OOS/OOT results, complaints, incidents and CAPA on the QA checks form as they occur, not at the end.
- Make sure each one has a documented impact assessment before the file goes to the QP.
- If an OOS is confirmed, reject promptly: the batch is rejected through a documented QP rejection declaration and the MAH is informed immediately.
Run activities in parallel, without cutting corners
Much of batch release does not depend on the final test result. The QA review of regulatory documents, CMO batch records, risk assessments and licences can be completed while samples are in transit and under test. So can preparation of the QP pack: the completed QA checklist and the draft batch release certificate.
Parallel working shortens the elapsed time between import and certification, but it does not change what must be true on the day. Certification still happens only when every item on the checklist is closed. Where a document is found to be unsatisfactory, request changes from the MAH or CMO at once and re-review; every day spent finding that gap early is a day not lost at the end.
Pre-certification readiness check
| Area | Confirm before handing the file to the QP |
|---|---|
| Regulatory | Current MA with post-approval comments; approved artwork; post-approval commitments and variations tracked |
| Manufacturing | BMR and BPR verified against the approved package; API, excipient and packaging COAs; validation and stability data |
| Risk assessments | Nitrosamine, elemental impurity and excipient risk assessments; TSE/BSE declaration |
| Sites and agreements | Licences checked against GMP database; audit reports available; technical agreements in place; supply chain diagram current |
| Transport and storage | Goods receipt reviewed; temperature or route validation data; physical condition confirmed; batch held in quarantine |
| Testing | Methods and specifications aligned to the approved package; COA reviewed and approved by QA; retention samples stored correctly |
| Non-conformances | Deviations, OOS/OOT, complaints, incidents and CAPA recorded, assessed and closed or justified |
| Labelling | Windsor Framework “UK Only” label verified, with a minimum font size of 7 |
Do not overlook labelling
Labelling checks are easy to forget until a batch arrives with the wrong pack. Sciom’s procedure builds a Windsor Framework check into the batch release checklist: medicinal product packaging distributed in the UK must carry the mandatory “UK Only” label, displayed with a minimum font size of 7. The addition of 2D barcodes, serial numbers or tamper-evident seals is optional, though they enhance medicine safety and regulatory compliance in the UK. For products placed on the market in the Union, Annex 16 separately expects that the safety features referred to in Article 54(o) of Directive 2001/83/EC have been affixed where appropriate.
After certification: close the loop
A batch is not available to the market the moment the QP signs. Annex 16 expects safeguards that stop uncertified batches reaching saleable stock, and a formal, unambiguous notification of QP certification to the site that will transfer stock. Good practice at this stage prevents a second round of delay:
- Send the QP certification to the storage site so quarantine stock can be moved to saleable stock, and share the batch release certificate with the MAH.
- Have the QP sign the QP register to record the batch details. Annex 16 requires certification to be recorded in a register or equivalent document, kept up to date and retained for at least five years.
- Maintain a batch release log from receipt to release that tracks import date, batch number, samples taken, COA approval, disposition decision, QP certification date, released quantity and stock transfer. It also provides an instant status view when the MAH asks “where is my batch?”.
How Sciom helps prevent delays
Sciom provides regulatory-compliant quality services that support the key stages of the pharmaceutical batch release process, aligned with UK and EU GMP expectations and focused on accuracy, reliability and documentation quality. Our batch release testing services bring testing, quality review and QP oversight into one coordinated workflow, so the gaps described above are found while there is still time to fix them. Specifically, we support batch release through:
- Qualified Person oversight to ensure each batch is certified in full compliance with UK/EU GMP requirements, including Annex 16.
- End-to-end batch documentation review covering manufacturing, packaging, testing, transport validation and deviation/OOS records.
- Integrated quality control and microbiological testing, reducing the delays that come with third-party coordination.
- Robust deviation, CAPA and change control assessment to support informed QP certification decisions.
- A strong focus on data integrity and documentation accuracy, so each batch release package is inspection-ready.
- Early identification and resolution of GMP issues, minimising batch release timelines and regulatory risk.
Our experience spans multiple dosage forms and product types, supporting both routine and complex batch releases. Learn more on our batch release testing page, or visit sciom.uk to explore our wider services.
Key takeaways
- Plan for certification on day one. Request the MA, artwork, batch records and risk assessments when the batch is planned, not when it lands.
- Review documents against the approved package, not merely for presence.
- Treat transport, storage and sampling as evidence, because Annex 16 requires the QP to consider them.
- Close investigations early. Open deviations and OOS results are the most common cause of late-stage surprises.
- Run QA review, testing and QP pack preparation in parallel, but never certify until the checklist is complete.
- Close the loop after certification: notify the storage site, share the certificate with the MAH, and sign the register.
The goal is not speed alone, but consistency and compliance. Batches that arrive complete move fast without compromising either.
Frequently Asked Questions
References and further reading
- EU GMP Annex 16: Certification by a Qualified Person and Batch Release (EudraLex Volume 4; published 12 October 2015, in operation from 15 April 2016)
- European Commission: EudraLex Volume 4, EU GMP Guidelines
- MHRA: UK Good Manufacturing Practice and Good Distribution Practice
- Directive 2001/83/EC of the European Parliament and of the Council (as amended)
- The Human Medicines Regulations 2012